Introduce SRS physical simulator and improvements
This MR consists of two parts:
- Introduces SRS physical simulator to test different configurations of
SRS
- Improvements in the SRS channel estimation (Addressing the comments
from old, unfinished MR !2875)
- rewrite nr_srs_channel_estimation() to loop over rx antennas and
antenna ports to be able to parallelize
- Improvements in timing_advance_offset and timing_advance_offset_nsec
computation
- Introduce SRS multi-symbol channel estimation
- The channel impulse response is estimated from the averaged
channel frequency response over multiple symbols
- The channel frequency estimates are left as they are to be able to
estimate doppler in the future
- Simplify SRS channel estimation to handle memory alignment in the
case of different SRS configurations (eg: comboffset)
To use multiple symbols when running gNB, the following parameters needs
to be edited in the function get_srs_resource()
- srs_res->resourceMapping.startPosition with a range from {0,1,..,5}
corresponds to the start symbol {13, 12, .. 8} with in a slot
- srs_res->resourceMapping.nrofSymbols indicates the number of symbols
{n1, n2, and n4}
Make sure the that start symbol + number of symbols is < 14
The timing results for SRS in develop and srs_phy_simulator are as follows:
Command used: sudo ./nr_ulsim -n1000 -s50 -S50 -R273 -W2 -y2 -z2 -E 1 -P
develop
|__ RX SRS time 124.94 us (1000 trials) (124.94 total [ms])
|__ Generate SRS sequence time 0.05 us (1000 trials) ( 0.05 total [ms])
|__ Get SRS signal time 19.41 us (1000 trials) ( 19.41 total [ms])
|__ SRS channel estimation time 89.11 us (1000 trials) ( 89.11 total [ms])
|__ SRS timing advance estimation time 13.10 us (1000 trials) ( 13.10 total [ms])
|__ SRS report TLV build time 2.80 us (1000 trials) ( 2.80 total [ms])
|__ SRS beam report build time 0.00 us ( 0 trials)
|__ SRS IQ matrix build time 2.73 us (1000 trials)
srs_phy_simulator
|__ RX SRS time 211.93 us (1000 trials) (211.93 total [ms])
|__ Generate SRS sequence time 0.04 us (1000 trials) ( 0.04 total [ms])
|__ Get SRS signal time 19.55 us (1000 trials) ( 19.55 total [ms])
|__ SRS channel estimation time 152.05 us (1000 trials) (152.05 total [ms])
|__ SRS timing advance estimation time 36.67 us (1000 trials) ( 36.67 total [ms])
|__ SRS report TLV build time 2.96 us (1000 trials) ( 2.96 total [ms])
|__ SRS beam report build time 0.00 us ( 0 trials)
|__ SRS IQ matrix build time 2.88 us (1000 trials)
Note that in srs_phy_simulator, to compute timing offset ns, an
oversampling factor of 2 is performed. Also, for peak detection, we
average the channel estimates for every port.
Remove schedule response and update L1 threading documentation
This merge requests removes the somewhat superfluous "schedule response"
mechanism. "schedule response" was run after running the scheduler
itself and copied various FAPI messages into a global msgDataTx
structure from which the various TX/RX jobs were triggered. It is not
necessary, though, given that the scheduler is run inside the tx_func()
(running the TX jobs of the L1), and so the scheduler output FAPI
messages can directly be read into a variable of the existing
NR_Sched_Rsp_t type. This allows to delete a couple of hundred lines of
code (while retaining functionality), and simplifies the msgDataTx type
(which is still there to trigger TX job (including the scheduler) from
the ru thread).
In short, prior, there was this call chain:
- tx_func() calls run_scheduler_monolithic() (through fptr
NR_slot_indication())
- get some memory through allocate_sched_response() which has enough
space for NR_Sched_Rsp_t type variable
- call the scheduler and fill the variable
- call nr_schedule_response() (through fptr NR_schedule_response())
which copies into L1: to msgDataTx for TX, to separate structures
for RX
this is changed to
- tx_func() runs one message at a time, hence we can use memory in the
data segment for NR_Sched_Rsp_t. It calls run_scheduler_monolithic()
through the fptr
- pointers into NR_Sched_Rsp_t are passed to the scheduler, which
fills as before
- we return, memory is in its right place and does not need an extra
copy.
Additionally, this merge request updates documentation on threading and
cleans up some unused code along the way.
Duplex is assumed to be static but for NTN bands, it is not static.
TxRX Duplex is defined in section 5.4.4 of 38.101-5 (for NTN) specs v1809
n256 190 MHz, 165 to 215 MHz
n255 -101.5 MHz, -72.5 to -130.5 MHz
n254 862 - 885 MHz
- Add to common/utils/nr/nr_common remove from NR_MAC_UE/nr_ue_procedures.c
- Adopt in asn1_msg.c for MeasurementReport: this solves the following assert:
Assertion (enc_rval.encoded > 0) failed!
In do_nrMeasurementReport_SA() /oai-ran/openair2/RRC/NR/MESSAGES/asn1_msg.c:898
ASN1 message encoding failed (MeasResultServMOList, 18446744073709551615)!
Motivation: unify RSRP-to-index mapping across layers and fix NR RRC MeasurementReport
encoding failures due to out-of-range values by reusing the validated mapping.
Note NR_RSRP-Range.c constraint:
{ APC_CONSTRAINED, 7, 7, 0, 127 } /* (0..127) */
- modify retrieve_ldpc_enc_op() to store encoded results in a packed format
- add timing measurements for T2 encoder
- add simde implementation for bit reversal
- Introduce new bit reversal implementation using simde_mm_gf2p8affine_epi64_epi8
instruction, based on https://wunkolo.github.io/post/2020/11/gf2p8affineqb-bit-reversal/.
This implementation requires GFNI and AVX512VL support on the target machine.
NR UE: consider the ratio of PUSCH EPRE to DMRS EPRE when calculating PUSCH
DMRS power scaling
When calculating DMRS scaling ratio, we should consider PUSCH EPRE to DMRS
EPRE according to TS 38.214 Table 6.2.2-1.
Close#929
Long PRACH extends beyond a slot. Changes necessary to mark future slots
that may contain prach in ru, phy and mac functions.
In RU, the PRACH IDFT is done only after receiving last slot and marks
for L1 to start processing. The L1 processes at the last prach slot and
reports to MAC with the first slot index.
In MAC scheduler, the VRB for future slots are also marked as used.
PRACH scheduler is called in advance one frame minus num prach slots.
Added Support of 35Mhz,45Mhz,70Mhz Bandwidth
Added Support of 35Mhz,45Mhz,70Mhz Bandwidth for 30Khz Subcarrier
Spacing, Also added 35Mhz, 45Mhz bw for 15Khz Subcarrierspacing.
Referred Spec TS 38.101 v18.6.0 section 5.3.2, table 5.3.2-1
Changes to support multiple TDD patterns
- Updated the configuration changes for 2 Patterns
- Update the TDD table configuration for NFAPI
- Added the tdd bitmap for the period
- Adapted the bitmap for UL/DL for the multi TDD pattern
- Updated the RACH procedure for multi TDD pattern
- Updated DL and UL scheduler for multi TDD pattern
* the function is returning the index of the first full UL slot in tdd_slot_bitmap
or the first UL slot (including mixed) if the "mixed" flag is provided
* set_tdd_bmap_period, config_tdd_patterns: to configure TDD period, including bitmap, in the frame structure
* get_tdd_periodicity: to retrieve the periodicity in milliseconds for the given TDD pattern
* get_tdd_period_idx: to get the TDD period index based on pattern periodicities
* get_ul_slots_per_period: get the number of UL slots (including mixed with UL symbols) in period
* get_full_ul_slots_per_period: get the number of full UL slots in period
* get_dl_slots_per_period: get the number of DL slots (including mixed with DL symbols) in period
* get_full_dl_slots_per_period: get the number of full DL slots in period
Co-authored-by: vijay chadachan <vijay.chadachan@firecell.io>
Implement run-to-completion for processSlotTX. This is achieved by using a new
dynamic_barrier_t which allows to specify callback after the first join has been
made.
Added support for NTN FDD FR1 bands 254, 255, 256 as specified in 3GPP TS 38.101-5
Conf files added for 15Khz, 5Mhz and 30Khz, 10Mhz configurations added for these bands