A new phy scope based on ImGui and ImPlot. This scope uses a different concurrency model than previous
scopes.
The PHY thread writing the data first checks if the data is ready to be written. If its not, nothing is copied.
The GUI thread reads data if available and marks it ready to write. This makes sure that the PHY threads are not
busy copying data that would never be displayed.
Some of the scopes also have a freeze functionality that further limit the amount of data that needs to be copied
from PHY threads. If a scope is "frozen" it still allows the user to explore the data using plots zoom/pan functions
but doesn't cause PHY threads to perform extra writes on the displayed data.
A compile option was added to enable/disable the scope. Use cmake -DENABLE_IMSCOPE=ON to enable the scope.
Update CXX standard to 17; it is required by some libraries (e.g., dear imgui). The oldest gcc version in
use by a distribution supported is Ubuntu 20, which has gcc 9.4 with c++17 support.
This assert and assumption is incorrect, according to 38.101-1 UE channel is defined only by the BWP size
and BWP size can be any value supported by the RRC parameters defining the BWP.
To determine the UE channel the smallest bandwidth supporting the BWP is selected. This is an assumption based
on references in the same document to UE channel bandwidth being equal to one of the values in set
{5, 10, 15, 20, 25, 30, 35, 40, 50, 60, 70, 80, 90, 100}.
Also:
- calculated P_CMIN during BWP setup since the parameter doesn't depend on DCI.
- initiialize uniqCfg structure in test_nr_ue_power_procedures main function which enables LOG prints during tests
- Reworked nrLDPC_decoder_offload.c to process all segments in a TB with a single call to LDPCdecoder() or LDPCencoder().
- Perform CRC checks on the T2.
- Modified nr_ulsch_decoding (gNB decoder) to:
- Count processed segments.
- Properly perform CRC checks.
- Created a constant NR_LDPC_MAX_NUM_CB to define the maximum number of codeblocks.
- Conditional library loading:
- On gNB: Load ldpc_t2 library if offload is enabled using the --ldpc-offload-enable flag.
- On UE: Load both ldpc_t2 and ldpc libraries since only encoder offload is supported.
- General cleanup of nrLDPC_decoder_offload.c for improved readability and maintainability.
- Modified the structure of LDPC encoder/decoder/offload parameters:
- Introduced a structure for code block (CB) related parameters.
- Removed parameter E from the encoder and offload parameter structures for clarity.
- Replaced E with perCB->E_cb in the UE encoder code.
- Phy config update and Sidelink frame parameters initialisation
- PSBCH scheduler to trigger TX PSBCH/RX PSBCH actions
- Sidelink indication with rx ind to trigger send SL-MIB to MAC
- Enable Scope for PSBCH use -d or --dqt
- Enable system testing of PSBCH for example using RFSIMULATOR:
- UE1 is a SYNCRONISATION SOURCE UE which transmits PSBCH
started using command -
sudo ./nr-uesoftmodem --sl-mode 2 --sync-ref 4 --rfsim --rfsimulator.serveraddr server
- UE2 syncs onto UE1 during sidelink search, gets the timing and continues to receive PSBCH
started using command -
sudo ./nr-uesoftmodem --sl-mode 2 --rfsim --rfsimulator.serveraddr 127.0.0.1
- In the default use case 2 Sidelink SSBs sent over 16 frames.
- In case SL-SSB configuration needs to be changed use -O option in the above command like
-O ../../../targets/PROJECTS/NR-SIDELINK/CONF/sidelink_preconfig_1txpool.conf
Till this commit, the UE gets the position of SSB in frequency from
command line and does the syncronization by locating the SSB in time. It
does this by generating a PSS time signal during initialization with the
SSB offset given via command line. Then PSS detection is done by
correlation.
In this commit, the UE computes a list of GSCN in the current NR band
that falls within the current bandwidth for the set center frequency.
For each GSCN in the list, the UE starts a thread and performs the
following:
1. Generate PSS time signal with SSB offset for current GSCN.
2. Detect PSS, SSS and decode PBCH (this step remains the same).
After all threads finishes, the results are collected.
For now, only the first detected PBCH is used to proceed further. So
this PBCH is indicated to MAC and UE exits initial sync.
Future work: The cell search can be standalone feature where the UE
could scan for SSB in the entire NR band. This would require changing
radio's frequency on the fly as the UE's bandwidth would not cover an
entire NR band. The cell detection can futher be imporved by looking
for SIB1 for each decoded PBCH.
nr_fill_indication() fills CRC and RX requests, to be sent from L1 to
L2. Before this commit, nr_fill_indication() is called when
- we finally decoded LDPC (or not)
- low signal on PUSCH
This might happen at the same time, i.e., nr_fill_indication() might try
to fill both CRC and RX, in the same list, from different threads. This
can lead to this assertion:
Assertion (crc->rnti == rx->rnti) failed!
In handle_nr_ulsch() ../../../openair2/NR_PHY_INTERFACE/NR_IF_Module.c:190
mis-match between CRC RNTI e071 and RX RNTI 5e3b
e.g., e071 is low energy, and while 5e3b related message are filled in
one thread, e071 is being put into the message structure as well.
At least that is my understanding. I could not actually reproduce this
assertion; to be seen if it still happens.
Do not assert if the list of phy statistics is full; instead return
NULL.
In most places, this is handled appropriately (we do not store anything
if we can't). In nr_decode_pucch0(), the return value of get_phy_stats()
is used a little bit all over the function, and a constant
if (uci_stats)
uci_stats->variable++;
would look ugly, so make uci_stats point to the stack if we cannot store
in the phy_stats.